• Print page
  • Email page

New York Court Applies Economic Loss Doctrine In Dismissing Surety's Lawsuit Against Architect

April, 2011

In Travelers Cas. & Surety Co. v. Dormitory Authority-State of New York, 734 F.Supp.2d 368 (S.D. N.Y. 2010), the United States District Court for the Southern District of New York was faced with a dispute over the construction of a fourteen story vertical campus for Baruch College in New York City.  The owner of the project entered into a contract with an architectural firm to provide all of the designs for the project, including contract drawings and specifications, bid documents and approve of all shop drawing, samples and substitutions proposed by the contractor. 

Ultimately, the contractor was unable to finish the project and its surety bond holder stepped in to complete the project.  The surety then brought suit against a number of parties involved in the construction project, including the designer.Since the contractor did not have a contractual relationship with the architectural firm, the surety's claims against the architect were based on professional negligence for the architect's alleged failure to provide clear and unambiguous bid documents as well as failing to provide timely interpretations of its designs.  The architect moved for summary judgment on the surety's professional negligence claims on the grounds that New York's economic loss doctrine barred the surety's tort claims.  In response, the surety argued that New York's negligent misrepresentation exception to the economic loss doctrine allowed it to pursue its professional negligence claims.

Under New York's negligent misrepresentation exception to the economic loss doctrine:

A defendant is liable where there is carelessness in imparting words upon which others were expected to rely and upon which they did act or failed to act to their damage, provided that such information was expressed directly with knowledge or notice that it will be acted upon, to one to whom the author is bound by some relation of duty, arising out of contract or otherwise, to act with care if he acts at all. 

After reviewing the facts of the case, the court held that there was not sufficient evidence of a contractual relationship or other close relationship between the contractor and the architect that would support the surety's claims.  In particular, the court found that the surety had failed to show that the contractor was known to the architect at the time it was preparing the bid documents.  Also, the  court found that the surety's failure to identify any specific misrepresentation prevented its negligence claims.  As such, the court dismissed the surety's negligence claims against the architect.

Back to CM Report on Construction (2011) 2011 Spring Table of Contents

Sign up for the CM Report

Stay on top of legal developments in your industry.

Sign up for the CM Report.

Back to CM Report on Construction (2011) 2011 Spring Table of Contents

Practice Areas

  • Construction Litigation
  • Fidelity & Surety
  • Professional Liability
  • First-Party Property

Industries

  • Architects and Engineers
  • Construction
  • Home
  • Our Firm
  • Practice Areas
  • Industries
  • Attorneys
  • News & Events
  • Publications
  • Client Resources
  • Industry Publications
  • Firm Publications
Search:
  • Careers
  • Contact Us
  • Brussels
  • Chicago
  • Düsseldorf
  • Irvine
  • London
  • New York
  • Paris
  • Parsippany
  • Rome
  • Shanghai
  • Wheaton
  • Site Map
  • Attorney Advertising
  • Disclaimer
  • Terms & Privacy Policy
  • © 2006 Clausen Miller PC